| Description | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Electrical installation — Phase 1 | 1 | lot | $18,500.00 | $18,500.00 |
| Conduit and cabling materials | 1 | lot | $4,200.00 | $4,200.00 |
| Panel board supply and installation | 2 | units | $3,100.00 | $6,200.00 |
| Site supervision (6 weeks) | 6 | weeks | $1,500.00 | $9,000.00 |
| Description | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Site survey and assessment | 1 | lot | $2,800.00 | $2,800.00 |
| Excavation and earthworks | 1 | lot | $24,000.00 | $24,000.00 |
| Regrading and compaction | 1 | lot | $18,500.00 | $18,500.00 |
| Drainage installation | 1 | lot | $12,000.00 | $12,000.00 |
| Project management | 1 | lot | $5,500.00 | $5,500.00 |